Railroad
Grade Separation Program
These projects either fail to satisfy the program goals, have initial estimates of excessive cost, |
||||||
|
Dist. |
Project |
Project Sponsor |
Rail Carrier |
Rough Project Cost |
Description |
Comments |
|
1 |
Allen - Bellefontaine Avenue |
Lima |
I&O |
$ 9.0 |
Construct underpass with retaining walls. |
Less than 30 trains/day, some isolation of emergency services. |
|
1 |
Allen - S. Main Street |
Lima |
CSXT, NS |
$ 16.0 |
Construct underpass with retaining walls. |
Nearby accessible grade separations exist, initial estimate of excessive cost. |
|
1 |
Allen - W. Fourth Street |
Lima |
CSXT |
$ 8.0 |
Construct grade separation to serve traffic flow from I-75 to industrial area. |
Severe negative impacts not demonstrated, no isolation of emergency services, does not meet program goals. |
|
1 |
Defiance - U.S. 127 |
Defiance County |
CSXT |
?? |
Construct grade separation somewhere in the Village of Sherwood. |
Severe negative impacts not demonstrated, trains move quickly - blockages are not lengthy. |
|
1 |
Defiance - S.R. 15 |
Defiance County |
CSXT |
?? |
Construct grade separation. Details are unknown. |
Project will have excessive impacts and cost at this location. TAG recommends Hire Road as alternative(see Tier 2). |
|
2 |
Sandusky - Durnwald Drive |
Clyde |
NS |
$ 3.9 |
Construct overpass with access road. |
Less than 30 trains/day & severe negative impacts not demonstrated. |
|
2 |
Wood - Union Street |
Walbridge |
CSXT |
$ 4.6 |
Construct overpass. |
Majority of population is not isolated from emergency services. Project would likely cause excessive impacts. Future CSX plans could relieve blocked crossing issue. |
|
2 |
Wood - S.R. 25 |
Perrysburg |
CSXT |
$ 6.0 |
Construct overpass with retaining walls. |
Less than 30 trains/day & severe negative impacts not demonstrated, no isolation of emergency services. |
|
2 |
Williams - U.S. 6 |
Edgerton |
NS |
$ 8.0 |
Construct grade separation. Details are unknown. |
Project would provide little benefit in relation to initial estimate of excessive impacts and cost. |
|
2 |
Williams - S.R. 49 |
Edgerton |
NS |
$ 6.0 |
Construct grade separation. Details are unknown. |
Project would provide little benefit in relation to initial estimate of excessive impacts and cost. |
|
2 |
Seneca - S.R. 101/S.R. 18 |
Tiffin |
CSXT |
?? |
Construct one grade separation and rework roadways. |
Problems are not that severe, nearby accessible grade separations exist. |
|
2 |
Seneca - S.R. 100 |
Tiffin |
CSXT |
?? |
Reconstruct existing deficient grade separation. |
Does not meet the goals of the program. |
|
2 |
Williams - N. Union Street |
Bryan |
NS |
?? |
Construct grade separation. Details are unknown. |
Severe negative impacts not demonstrated, trains move quickly - blockages are not lengthy. |
|
3 |
Lorain - Highbridge Road |
Vermilion |
NS |
$ 1.5 |
Construct new bridge over NS tracks (old bridge was removed in 1980's). |
Does not meet the goals of the program, strong local opposition. |
|
3 |
Erie - Douglas Street |
Vermilion |
NS |
?? |
Construct overpass with retaining walls. |
Less than 30 trains/day & severe negative impacts not demonstrated. |
|
3 |
Crawford - S.R. 103 |
Crawford County |
NS |
$ 2.7 |
Construct overpass. |
Less than 30 trains/day & severe negative impacts not demonstrated. |
|
3 |
Crawford - E. Beal Avenue |
Bucyrus |
NS |
$ 3.0 |
Construct overpass. |
Less than 30 trains/day & severe negative impacts not demonstrated. |
|
3 |
Lorain - Kansas Avenue |
Lorain |
NS |
$ 7.1 |
Construct underpass. |
Less than 30 trains/day & severe negative impacts not demonstrated. |
|
3 |
Huron - S.R. 13 (#142117A) |
Greenwich Twp. |
CSXT |
?? |
Construct overpass. |
Less than 30 trains/day & severe negative impacts not demonstrated. |
|
4 |
Ashtabula - S.R. 193 |
North Kingsville |
CSXT |
$ 2.8 |
Construct overpass. |
Severe negative impacts not demonstrated, trains move quickly - blockages are not lengthy, no isolation of EMS. |
|
4 |
Summit - Stow Road |
Hudson |
NS |
$ 10 |
Construct overpass. |
Project declared infeasible. R/W and community impacts of project were too great. City elected not to further pursue project |
|
4 |
Summit - New Local Road |
Twinsburg |
WLE |
$ 0.6 |
Proposed new roadway connecting Ravenna and Darrow Roads. |
Does not meet the goals of the program, problems are not that severe. |
|
4 |
Stark - S.R. 44 |
Louisville |
NS |
$ 4.0 |
Construct overpass on new roadway alignment. |
Less than 30 trains/day & severe negative impacts not demonstrated, does not meet the goals of the program. |
|
4 |
Summit - Evans Avenue |
Akron |
CSXT |
$ 7.2 |
Construct overpass. |
Less than 30 trains/day & severe negative impacts not demonstrated, blockages are not lengthy. |
|
4 |
Summit - Broad Boulevard |
Cuyahoga Falls |
CSXT |
$ 8.0 |
Construct grade separation. Details are unknown. |
Less than 30 trains/day & severe negative impacts not demonstrated, blockages are not lengthy, nearby grade separations. |
|
4 |
Summit - Bailey Road |
Cuyahoga Falls |
CSXT |
$ 6.0 |
Construct grade separation. Details are unknown. |
Less than 30 trains/day & severe negative impacts not demonstrated, blockages are not lengthy, nearby grade separations. |
|
4 |
Summit - S.R. 91 |
Munroe Falls |
CSXT |
?? |
Construct grade separation. Details are unknown. |
Through trains move quickly, blockages are not as lengthy as other sites. Problem with malfunctioning gates - check with PUCO. |
|
6 |
Franklin - Hard Road |
Columbus |
CSXT |
$ 6.5 |
Construct underpass with road widening project. |
Project is fully funded locally, blockages are not that lengthy. |
|
6 |
Marion - S.R. 309 |
Marion |
CSXT |
$7.50 |
Construct overpass. |
Project declared infeasible. R/W and community impacts of project were too great. |
|
6 |
Marion - C.R. 162 @ S.R. 4 |
Marion |
NS |
$ 3.4 |
Construct overpass and provide access road from C.R.162 to S.R. 4. |
Area is mostly industrial and blockages do not isolate residential areas. R/W costs could make project infeasible. |
|
7 |
Darke - Dearfield Road |
Union City |
CSXT |
?? |
Construct grade separation. Details are unknown. |
Severe negative impacts not demonstrated, no true isolation of emergency services, cost & impacts could be excessive. |
|
7 |
Miami - Donn Davis Way |
Tipp City |
CSXT |
$ 4.0 |
Proposed new roadway. |
Does not meet the goals of the program, problems are not that severe. |
|
7 |
Montgomery - Sellars Road |
Moraine |
NS |
$ 3.2 |
Construct grade separation. Details are unknown. |
Severe negative impacts not demonstrated, no true isolation of emergency services. |
|
8 |
Hamilton - Beech Street |
St. Bernard |
NS |
$ 5.0 |
Construct underpass. |
Blockages are not lengthy, nearby grade separation provides access, no true isolation of emergency services. |
|
8 |
Butler - Central Avenue |
Hamilton |
CSXT |
?? |
Construct grade separation. Details are unknown. |
No isolation of emergency services, nearby grade separation provides access, impacts are traffic related only. |
|
12 |
Cuyahoga - London Road |
Cleveland |
NS |
$ 1.4 |
Construct underpass. |
Less than 30 trains/day & severe negative impacts not demonstrated, blockages are not lengthy, nearby grade separation. |
|
12 |
Cuyahoga - Nottingham/Dille |
Cleveland |
NS |
$ 0.2 |
Construct underpass. Applicant requests $155K for P.E. |
Less than 30 trains/day & severe negative impacts not demonstrated, blockages are not lengthy. |
|
12 |
Cuyahoga - W. Grace Street |
Bedford |
NS, WLE |
$ 0.7 |
Extend Mapledale Ave. to connect W. Grace St. to Powers Rd. |
Does not meet the goals of the program, problems are not that severe, nearby grade separation provides access. |
|
12 |
Cuyahoga - Chardon Road |
Euclid |
NS |
$ 7.5 |
Construct grade separation. Details are unknown. |
Less than 30 trains/day & severe negative impacts not demonstrated, blockages are not lengthy. |
|
12 |
Lake - Lost Nation Road |
Willoughby |
CSXT, NS |
$ 15.0 |
Extend Lost Nation Rd. from Pelton Rd. to U.S. 20. |
Initial estimates of excessive cost and impacts. |
|
12 |
Lake - S.R. 633 (Lloyd Road) |
Wickliffe |
CSXT, NS |
$ 6.0 |
Construct overpass. |
Nearby accessible grade separation exists, no isolation of emergency services. |
|
12 |
Lake - Liberty Street |
Painesville |
NS |
$ 12.0 |
Construct overpass. |
Less than 30 trains/day & severe negative impacts not demonstrated, blockages are not lengthy. |
|
Total |
$ 252.8 | |||||
|
Note: For projects of unknown cost, rough estimates of $3 million and $7 million were used for rural and urban locations respectively. |
||||||