construction | contracts | districts | engineering | financial | odot home | intranet | otis | policy | services
TRAC Home | Tier I List | Complete List in PDF format
| 2001-2007 Major New Program Tier II - Projects to Be Continued for Some Stage of Development May 29th, 2003 |
|||||||||
| The following list explains the project development activities for the Tier II Major New Construction Projects. | |||||||||
|
|||||||||
|
Dist. |
Project |
PID |
Cost |
Demo |
Commitment |
Description |
2003 |
2004 |
2005 |
2006 |
2007 |
|
Tier II Funding Commitments |
|||||||||||
|
1 |
Defiance US 24 |
24337 |
$26.6 |
|
$2.5 |
Add additional 2 lanes ffrom SR 424 to SR 15 |
|
$2.5 |
|||
|
1 |
Paulding/Defiance US 24 |
24336 |
$42.2 |
|
$3.5 |
Relocate US 24 from US 127 to SR 424 near Defiance |
|
$3.5 |
|||
|
1 |
Paulding US 24 |
24335 |
$22.7 |
|
$1.2 |
Relocate US 24 from TR 69 east of Antwerp to US 127 |
|
$1.2 |
|||
|
1 |
Defiance/Henry US 24 |
19047,24339 |
$20.1 |
|
|
Add additional 2 lanes ffrom SR 281 to Napoleon |
|
$0.9 |
|
|
|
|
2 |
Henry/Lucas US 24 |
17893, 20404 |
$153.4 |
$5.7 Demo |
$20.0 |
Widen US 24 from Napoleon to Waterville |
|
$9.6 |
$10.0 |
|
|
|
2 |
Lucas I-75/I-475 |
23648 |
$30.0 |
$1.0 Demo |
$6.0 |
Upgrade Interchange of I-75 and I-475 Phase 1 |
|
$3.0 |
$3.0 |
||
|
2 |
Lucas I-475 |
75937 |
$61.0 |
$6.0 Local R/W |
$0.9 |
Upgrade Interchange of I-475 and Salisbury Road |
|
$0.9 |
|||
|
4 |
Summit I-77 |
16514 |
$45.1 |
|
$2.4 |
Widen I-77 from SR 162 (Copley Rd) and SR 21 |
$1.4 |
|
$1.0 |
||
|
4 |
Summit SR 8 |
24507,24508 |
$120.0 |
$1 County |
$13.2 |
Convert roadway to a four-lane limited access from SR 303 to I-271 |
$10.2 |
$3.0 |
|
|
|
|
4 |
Mahoning/Trumbull US 62 |
9566 |
$45.3 |
2.5 Demo |
$2.7 |
Hubbard Arterial alternative US 62F to I-80 |
|
|
$2.7 |
|
|
|
5 |
Franklin/Licking SR 161/SR 37 |
12139 |
$42.4 |
First phase only |
$20.3 |
Widen SR 161/SR 37 to four lanes to connect Newark and Columbus |
$5.0 |
$15.3 |
|
|
|
|
6 |
Franklin I 70 / 71 Split |
23318 |
$400.0 |
|
$6.0 |
Needs study of the downtown Columbus Interstates |
|
$6.0 |
|
|
|
|
6 |
Franklin I-670 Intl. Gateway |
75293 |
$39.3 |
$15 Airport |
$1.5 |
Upgrade the Stelzer/Intl. Gateway intersection to a interchange |
$1.5 |
|
|
|
|
|
6 |
Franklin/Delaware North Rail |
75306 |
$433.7 |
|
$2.5 |
New Passenger Rail facility from downtown to Polaris |
$2.5 |
|
|
|
|
|
7 |
Montgomery I-75 |
75927 |
$400.0 |
$1.8 SPR |
$18.0 |
Upgrading I-75 in Downtown Dayton |
|
$11.0 |
$5.0 |
|
|
|
8 |
Butler I-75/SR 63 |
10752 |
$44.5 |
|
$8.3 |
Reconstruct and expand I-75/SR 63 Interchange |
|
|
$6.0 |
|
|
|
8 |
Hamilton I 75 |
20835 |
$800.0 |
|
$3.0 |
Upgrading I 75 in Hamilton County |
|
$3.0 |
|
|
|
|
8 |
Eastern Corridor Study |
No PID |
$22.0 |
$5.0 |
$4.4 |
Improve the East/West movement on the east side of Cincinnati |
$2.7 |
|
|
|
|
|
10 |
Hocking/Athens US 33 |
14040,23846 |
$58.5 |
|
$9.0 |
Nelsonville Bypass, Phase I |
$2.5 |
|
|
|
|
|
10 |
Hocking/Athens US 33 |
14040 |
$50.0 |
|
$0.8 |
Nelsonville Bypass, Phase II |
|
$0.8 |
|
|
|
|
10 |
Washington SR 7 |
?? |
$23.7 |
|
$0.4 |
Improve SR 7 on the eastside of Marietta |
|
$0.4 |
|
|
|
|
11 |
Stark/Columbiana US 30 |
20344 |
$42.0 |
|
$6.0 |
Relocate US 30 from Trump Ave. to SR 44 |
|
$3.6 |
|
|
|
|
12 |
Cuyahoga I-77 |
22222 |
$34.3 |
|
$2.5 |
Widen I-77 from SR 82 to Pleasant Valley Rd. |
|
$2.5 |
|
|
|
|
12 |
Cuyahoga Central Viaduct/Innerbelt Study |
|
$400.0 |
$6 District |
$12.0 |
Needs study of the downtown Cleveland interstates |
|
$12.0 |
|
|
|
|
$25.8 |
$79.2 |
$17.7 |
$10.0 |
$0.0 |
|||||||
| Additional Tier II Projects Under Development | |||||||||||
|
1 |
Defiance US 24 |
24338 |
$15.5 |
|
|
Extend 4-lanes and Construct Interchange at SR 281 near Defiance |
District Designing project in house |
||||
|
1 |
Paulding US 24 |
24334 |
$32.6 |
|
|
Relocate US 24 from Indiana State line to TR 69 east of Antwerp |
District Designing project in house |
||||
|
1 |
Hancock US 30 |
12421 |
$23.1 |
$ RW Demo |
$0.7 |
Relocate US 30 from US 68 to SR 37 |
Right-of-way completed awaiting construction |
||||
|
1 |
Hancock US 30 |
12420 |
$39.3 |
$ RW Demo |
$0.8 |
Relocate US 30 from SR 235 to US 68 |
Right-of-way completed awaiting construction |
||||
|
1 |
Hancock/Wyandot US 30 |
12422 |
$50.8 |
$ RW Demo |
$0.3 |
Relocate US 30 from SR 37 to Upper Sandusky |
Right-of-way completed awaiting construction |
||||
|
2 |
Wood I-75 |
23890 |
$9.2 |
|
|
New Interchange at I-75 north of Bowling Green |
Awaiting completion of Interchange Justification Study |
||||
|
3 |
Sandusky/Huron US 20 |
12061 |
$30.0 |
|
|
Bellvue Transportion Study |
Studying alternative solutions |
||||
|
4 |
Akron Metro CAC Rail |
|
$250.0 |
|
|
Canton-Akron-Cleveland Commuter Rail project |
MIS resulting projects to come to TRAC 2003 |
||||
|
4 |
Stark/COL/MAH US 62/ SR 14 |
4089/12122 |
$59.8 |
2.9 Demo |
|
New limited access four-lane from Salem to Alliance |
Review Environmental Documents |
||||
|
4 |
Summit SR 8 |
11661 |
$6.0 |
$3.0 City |
|
New Interchange SR 8 at Seasons Rd. |
Local Pursuing further development |
||||
|
4 |
Summit / Mahoning I 76/80 |
23676 |
$250.0 |
|
|
Corridor Improvments |
Currently Under study |
||||
|
5 |
Franklin/Fairfield US 33 |
23152 |
$135.0 |
|
$5.0 |
Upgrade US 33 Columbus to Lancaster to interstate standards |
Complete Preliminary Engineering |
||||
|
5 |
Muskingum - SR 93 |
20428 |
$18.8 |
$0.5 High Priority |
|
SR 93 / 22 Connector |
Preliminary development |
||||
|
6 |
Franklin - IR 270 |
25733 |
$28.5 |
$28.5 District |
$0.0 |
Pavement Rehab, Lane Addition from US 23 to I-71 on Southside |
Currently Under study |
||||
|
6 |
Franklin ITS |
No PID |
$43.0 |
|
|
Columbus ITS |
Currently Under Design |
||||
|
7 |
Champaign US 68 |
9927 |
$19.0 |
$3.0 County/City |
|
Bypass of Urbana |
Awaiting completion of environmental studies |
||||
|
7 |
Montgomery I-75 |
10697 |
$80.0 |
|
|
Build a new interchange in southern Montgomery County near Austin Rd. |
Locals Completing IJS |
||||
|
8 |
Butler SR 63 |
No PID |
$0.2 |
$0.2 County |
|
Oxford to Monroe corridor improvement study |
Locals Performing Corridor Study |
||||
|
8 |
Clermont I-275/SR 32 |
22972 |
$0.5 |
|
$0.5 |
Upgrade the I-275 and SR 32 Interchange area |
Complete Preliminary Engineering |
||||
|
8 |
Hamilton I-71 Transit Corridor |
19139 |
$539.7 |
$65 Locals/FTA |
$7.0 |
Ohio portion of Ohio-Kentucky LRT ( light rail transit) |
Preliminary Engineering funded |
||||
|
8 |
Hamilton I-275 |
|
$90.0 |
$82 Multi-lane |
|
Widen I-275 from SR 4 to US 42 |
Development by District office |
||||
|
8 |
Warren I-75/SR 122 |
No PID |
$16.0 |
|
|
Upgrade the interchange of I-75 and SR122 |
Awaiting completion of Interchange Justification Study |
||||
|
9 |
Ross SR 104 |
21250 |
$9.8 |
|
|
Widen SR 104 from US 35 to SR 207 |
Locals Developing Project |
||||
|
12 |
Lake I-90 |
5774 |
$25.3 |
$18 Multi-lane |
|
Widen I-90 from SR 306 to SR 615 |
Development by District office |
||||