Draft Major New
Construction Program Tier I - Projects for Construction SFYs 2002-2006 APPROVED May 24, 2002 |
|||||||||||||
|
The following projects are draft selection for construction in State Fiscal Years 2002-2006z. Projects are subject to change if fiscal projections change. The figures denoted for project revenue are estimated as a planning tool only. All revenue amounts are subject to future federal authorization |
|||||||||||||
|
|||||||||||||
| Dist. | Project | PID | Cost | Demo | Commitment | Description |
2002 |
2003 |
2004 |
2005 |
2006 |
|
2 |
Lucas SR 2 |
16387 |
$13.9 |
|
$13.9 |
Widen Toledo Airport Highway to six lanes |
$9.2 |
|
|
|
|
|
|
|
16387 |
|
|
|
|
$3.0 |
|
|
|
|
|
2 |
Maumee River Crossing |
20786 |
$391.0 |
$50 Demo / $8.5 Dist. |
$332.5 |
Replace current lift bridge with a new structure |
|
|
$5.5 |
|
|
|
|
|
21499 |
|
|
|
|
|
$9.3 |
|
|
|
|
|
|
19649, 19650, 19651, 20941 |
|
$4.0 Disc. |
|
|
Sold FY 2001 |
|
|||
|
|
|
20208, 21891, 21893, 21895 |
|
|
|
Main Span / Purchase Cable Stay Inspection & Testing |
Bonded - Sells in FY 2002 & 2004 |
|
|||
|
2 |
Maumee bond payments |
22389 |
|
|
|
|
$15.0 |
$25.0 |
$25.0 |
$25.0 |
$25.0 |
|
2 |
Lucas SR 2 |
23569,23570,23572 |
$19.0 |
$5.0 Demo |
$14.0 |
Safety Upgrading on SR 2 frm Oregon to Port Clinton |
$0.5 |
|
$6.5 |
$7.0 |
|
|
2 |
Sandusky SR 53 |
9443 |
$11.3 |
|
$11.3 |
Widen SR 53 from US 6 (Fremont Bypass) to Turnpike |
$0.5 |
|
$10.8 |
|
|
|
2 |
Wood US 20/SR 420 |
20213 |
$18.5 |
$5.0 Demo |
$13.5 |
Upgrade of the US 20/SR 420 intersection near Lemoyne Rd. |
$0.9 |
$1.8 |
$10.8 |
|
|
|
|
|
20213 |
|
|
|
|
$0.9 |
|
|
|
|
|
3 |
Black River Intermodal |
20339 |
$7.0 |
$3.5 Demo |
$3.5 |
Intermodal facility in Lorain County |
$3.5 |
|
|
|
|
|
3 |
Crawford/Richland US 30 |
16284 |
$129.8 |
|
$129.8 |
New four-lane highway from Stetzer Rd. to SR 314 |
$38.0 |
|
|
|
|
|
|
|
16284 |
|
|
|
|
$0.5 |
|
|
|
|
|
|
|
16283 |
|
|
|
|
$1.5 |
|
|
|
|
|
|
|
16283 |
|
|
|
|
$40.0 |
|
|
|
|
|
|
|
16282 |
|
|
|
|
$2.0 |
$38.0 |
|
|
|
|
3 |
Medina I-71/SR 18 Interchange |
20397 |
$9.5 |
$0.1 Locals |
$9.4 |
Improve the I-71/SR 18 interchange and widen SR 18 |
$1.5 |
|
$7.0 |
|
|
|
3 |
Medina I-71 |
14017 |
$53.0 |
$47.1 ML/Dist |
$5.9 |
Widen I-71 from Wayne C.L. to I-76 |
|
|
|
$5.9 |
|
|
3 |
Medina SR 18 |
4082 |
$20.0 |
$9.4 Local/Demo |
$10.6 |
Widen SR 18 from Windfall Rd. to Summit C.L. |
|
|
|
$10.6 |
|
|
3 |
Richland I-71 |
18632 |
$37.0 |
$32.8 Dist/ML |
$4.2 |
Add a lane from SR 97 to Mansfield-Lucas Rd. |
|
|
$4.2 |
|
|
|
3 |
Richland I-71 |
19956 |
$32.5 |
$29.0 Dist/ML |
$3.5 |
Add a lane from Morrow C.L. to SR 97 |
|
|
$3.5 |
|
|
|
3 |
Wayne I-71 |
14016 |
$33.6 |
$29.9 Dist/ML |
$3.7 |
Add a lane from Ashland C.L. to Medina C.L. |
$3.7 |
|
|
|
|
|
3 |
Wayne US 30 |
16285 |
$87.9 |
$25 Demo |
$62.9 |
New four-lane facility from Wooster to Kansas Rd. |
$3.0 |
|
$36.0 |
|
|
|
|
|
16287 |
|
|
|
|
Demo |
|
$24.0 |
|
|
|
4 |
Mahoning I-80/SR 46 |
9016 |
$12.3 |
$3.8 MPO |
$8.5 |
Interchange upgrade at SR 46 |
|
|
$8.5 |
|
|
|
4 |
Mahoning I-80 |
6080 |
$53.8 |
$40.7 ML/MB/Dist |
$13.1 |
Widen I-80 and replace twin bridges over the Meander Reservoir |
$2.8 |
|
|
$10.3 |
|
|
4 |
Stark I-77 |
23482 |
$7.6 |
$3.8 County |
$3.8 |
New interchange at I-77 & Shuffel Rd. |
Locals |
Locals |
$3.7 |
|
|
|
4 |
Ashtabula SR 45 |
20357 |
$7.4 |
$4.6 Demo |
$2.8 |
Widen SR 45 to eliminate bad alignment |
|
$1.0 |
|
|
|
|
4 |
Mahoning/Trumbull SR 711 |
20753/7386 |
$73.4 |
$25.0 Demo |
$30.6 |
Construct a new four-lane facility between I-680 and I-80 |
|
$1.8 |
|
|
|
|
|
|
20754 |
|
$5.8 Dist/$12.0 MB |
|
|
$2.0 |
|
$17.4 |
|
|
|
|
|
|
|
|
|
|
$0.6 |
|
|
|
|
|
|
|
|
|
|
|
|
$0.1 |
|
|
|
|
|
4 |
Stark I-77 |
20410 |
$106.9 |
$8.1 Dist |
$98.8 |
Upgrading of I-77 in Canton from US 30 to US 62 |
$2.2 |
|
$38.3 |
|
|
|
|
|
20412 |
|
|
|
|
$1.7 |
|
$2.0 |
$34.6 |
|
|
|
|
19563 |
|
|
|
PR for STA 77 PID 20411, 20410, 20412, 16637, 21609, 21610, 16372 |
$2.3 |
|
|
|
|
|
4 |
Stark SR 297 |
4081 |
$5.2 |
|
$5.2 |
Widen Whipple Ave. from 7th St. to 11th St. in Stark County |
$4.0 |
|
|
|
|
|
4 |
Stark/Summit I-77 |
16367 |
$82.3 |
|
$82.3 |
Widen I-77 from US 62 to Akron-Canton Airport |
$23.3 |
|
|
|
|
|
|
|
21609 |
|
|
|
|
|
$19.5 |
|
|
|
|
|
|
21610 |
|
|
|
|
$1.7 |
|
|
$35.6 |
|
|
4 |
Summit SR 8 |
20356 |
$47.0 |
|
$47.0 |
Major improvements to upgrade SR 8 in Akron |
|
$39.0 |
|
|
|
|
5 |
Fairfield US 33 |
16295 |
$153.5 |
|
$153.5 |
Lancaster Bypass |
$6.0 |
$23.0 |
|
|
|
|
|
|
16294 |
|
|
|
|
$25.0 |
|
|
|
|
|
|
|
16293 |
|
|
|
|
|
|
|
|
|
|
|
|
23057 |
|
|
|
|
|
$23.0 |
|
|
|
|
5 |
Guernsey SR 209 |
11723 |
$5.7 |
$2.2 Demo |
$3.5 |
Widen to five lanes south of the industrial park |
Demo |
$3.5 |
|
|
|
|
5 |
Fairfield US 33 |
13281 |
$23.9 |
$4.0 Demo |
$19.1 |
Upgrade Hill/Diley intersection to an interchange |
$12.6 |
|
|
|
|
|
|
|
13281 |
|
$0.7 Rail |
|
|
$2.5 |
|
|
|
|
|
5 |
Licking SR 79 |
8314 |
$15.7 |
$9.2 Demo/$.7 Enhan. |
$5.9 |
Widen to five lanes from Hebron Bypass to existing five-lane |
$3.8 |
Dem/Enh |
|
|
|
|
6 |
Franklin I-670 |
14225 |
$16/yr |
|
|
Spring Sandusky Interchange (SR 315 & I-670) |
$16.0 |
$16.0 |
$16.0 |
$16.0 |
$16.0 |
|
6 |
Franklin SR 315 (OSU Ramps) |
7930 |
$8.3 |
$3.5 Demo |
$4.8 |
New interchange accessing OSU Hospital |
|
$4.3 |
|
|
|
|
|
|
7930 |
|
|
|
|
$0.5 |
|
|
|
|
|
6 |
Franklin Multimodal Terminal |
22503 |
$23.7 |
$10.6 COTA/FTA |
$13.1 |
Construct a multi-modal center in downtown Columbus |
|
|
$13.1 |
|
|
|
6 |
Franklin I-270/SR 161 |
12557 |
$112.0 |
|
$112.0 |
SR 161/I-270 and SR 161/Sunbury interchange upgrades |
$3.0 |
|
|
$43.0 |
|
|
|
|
12563 |
|
|
|
|
$2.0 |
|
|
|
$60.0 |
|
7 |
Darke County, Versailles |
21048 |
$4.9 |
|
$4.9 |
Transportation Study |
$0.5 |
$3.9 |
|
|
|
|
7 |
Montgomery I-70/I-75 |
19069 |
$142.1 |
|
$142.1 |
Reconstruct and expand I-70/I-75 Interchange |
|
$4.1 |
|
$42.6 |
|
|
|
|
18249 |
|
|
|
|
$27.9 |
|
|
|
|
|
|
|
19070 |
|
|
|
|
$4.5 |
$41.9 |
|
|
|
|
7 |
Montgomery I-70 |
22935 |
$29.1 |
$17 District |
$12.1 |
Widen I-70 from I-75 to Clark C.L. |
|
|
|
|
$12.1 |
|
8 |
Bulter TID Bond Payments |
|
$12/yr |
|
|
Butler Transportation Improvement District bond payments |
$12.0 |
$12.0 |
$12.0 |
$12.0 |
$12.0 |
|
8 |
Butler SR 63 extension |
20499 |
$41.9 |
$14.2 County |
$27.7 |
SR 63 extension (Trenton Bypass) |
Devel. by Locals |
|
$27.7 |
|
|
|
8 |
Hamilton Transit Center |
23089 |
$3.7 |
$1.0 Locals |
$2.7 |
Knowlton's Corner Transit Center |
Devel. by Locals |
$2.7 |
|
|
|
|
8 |
Clermont/Hamilton I-275 |
12436, 10914 |
$52.5 |
$10 District |
$42.5 |
Add lane from US 50 to Five Mile Rd. |
$42.5 |
|
|
|
|
|
8 |
Greene US 35 |
20009 |
$20.0 |
$4.0 Demo |
$16.0 |
New interchange at North Fairfield Rd. |
$12.0 |
|
|
|
|
|
8 |
Hamilton I-275 (Reed Hartman) |
20128 |
$16.4 |
$7.5 Locals |
$8.9 |
Interchange improvements and auxiliary lane to US 42 |
$8.9 |
|
|
|
|
|
8 |
Hamilton/Butler I-75 |
10751 |
$44.9 |
|
$44.9 |
Widen I-75 to accommodate Union Center Blvd. interchange |
|
$44.0 |
|
|
|
|
8 |
Clermont SR 32 |
20056 |
$7.0 |
$3.5 County |
$3.5 |
Upgrade Stonelick Olive Branch intersection to an interchange |
$3.5 |
|
|
|
|
|
8 |
Clermont US 50 |
20028 |
$1.0 |
$0.5 County |
$0.5 |
Upgrade interchange on US 50 |
$0.5 |
|
|
|
|
|
9 |
Ross SR 207/US 23 Connector |
18492 |
$25.0 |
$2.5 |
$22.5 |
Construct a connector between SR 207 and US 23 |
|
$1.0 |
|
$21.5 |
|
|
11 |
Tuscarawas I-77/CR 80 |
19734 |
$9.0 |
$7.0 Demo |
$2.0 |
New interchange at CR 80 in Dover |
|
Demo |
$0.5 |
|
$1.3 |
|
11 |
Harrison/Belmont US 250 |
18365 |
$27.0 |
$23 Demo |
$4.0 |
Construct Super 2 highway on new location |
Demo Money |
$4.0 |
|
|
|
|
12 |
Lake US 20 |
8411 |
$8.5 |
|
$8.5 |
Widen US 20 from Mentor C.L. to Fern Rd. in Painesville |
|
$0.9 |
|
$7.6 |
|
|
12 |
Cuyahoga I-480/Brookpark |
21206 |
$23.7 |
$8.3 Locals |
$15.4 |
Relocation of Brookpark Rd. and the I-480/Grayton Rd. interchange |
$15.4 |
|
|
|
|
|
12 |
Cuyahoga Bessemer Ave. |
20329 |
$8.0 |
$1.8 Locals |
$6.2 |
Extension of Bessemer Ave. to increase connectivity to I-490 |
$0.6 |
$2.6 |
$2.8 |
|
|
|
12 |
Cuyahoga I-90 |
19673 |
$11.7 |
7.7 District |
$4.0 |
Add auxiliary lanes on I-90 between US 20 and SR 84 |
|
$2.7 |
|
|
|
|
12 |
Cuyahoga SR 82 |
7848 |
$12.0 |
$8 Demo/Local |
$4.0 |
Widen sections in Strongsville |
|
|
$4.0 |
|
|
|
|
|
20340 |
$4.0 |
$2.5 Demo |
$1.5 |
Intersection improvements in North Royalton |
|
|
$1.5 |
|
|
|
|
|
20342 |
$3.0 |
$2.5 Demo |
$0.5 |
Intersection improvements in Broadview Heights |
$0.5 |
|
|
|
|
|
|
|
|
Project |
Local |
Total TRAC |
|
|
|
|
|
|
|
Dist. |
Project |
PID |
Cost |
Demo |
Commitment |
Description |
2002 |
2003 |
2004 |
2005 |
2006 |
|
|
|
9222/5557 |
$7.0 |
$4.4 Local/Dist |
$2.6 |
Widen Royalton Rd (SR 82) in Strongsville |
|
$0.6 |
$2.0 |
|
|
|
12 |
Cuyahoga SR 91 |
20334 |
$13.0 |
$4.0 Local |
$9.0 |
Widen S.O.M. Center Rd. between White Rd.and Sandalwood |
$1.0 |
$8.0 |
|
|
|
|
12 |
Cuyahoga SR 91 |
7900 |
$7.9 |
$5.8 City of Solon |
$2.1 |
Widen S.O.M. Center Rd. in Solon |
$2.0 |
|
|
|
|
|
12 |
Cuyahoga SR 322/I-271 |
12472 |
$13.1 |
$1.9 city |
$11.2 |
Upgrade interchange and improve Mayfield Rd. |
|
|
|
$11.2 |
|
|
12 |
Cuyahoga SR 237 |
23051 |
$42.7 |
$26.2 Local |
$16.5 |
Improve SR 237 ramps servicing Hopkins Airport |
|
|
|
$16.5 |
|
|
12 |
Lake SR 84 |
9247 |
$9.1 |
$3.3 Local |
$5.8 |
Widen SR 84 from I-90 to US 6 |
|
|
|
$5.8 |
|
|
12 |
Euclid Avenue Corridor |
20332 |
$350.0 |
$280 FTA/Locals |
$70.0 |
Euclid Corridor improvements |
$3.5 |
$37.0 |
$26.0 |
|
|
|
|
|
|
|
|
|
|
Funding Predicated on Local Match |
|
|
|
|
|
12 |
Lake SR 615/I-90 |
9332 |
$4.9 |
$4.6 Demo |
$1.6 |
New interchange at I-90 and SR 615 |
|
|
|
|
|
|
|
|
9331 |
$9.6 |
|
$7.9 |
|
$7.0 |
|
|
|
|
|
|
|
12790 |
$1.7 |
|
$1.7 |
|
Sold FY 2001 |
|
|||
|
12 |
Lake US 20 |
20343 |
$5.0 |
$5.0 Demo |
$0.0 |
Upgrade intersections in Perry, Painesville, and Madison |
Demo |
Demo |
|
|
|
|
|
|
|
|
|
|
|
$378.1 |
$363.9 |
$287.8 |
$332.9 |
$126.4 |
|
Southeast Ohio Plan |
|||||||||||
|
SE Ohio Plan Construction Bond Payments |
$17.0 |
$17.0 |
$17.0 |
$17.0 |
$17.0 |
||||||
|
(The following project construction costs are shown for informational purposes and are fully funded by the bond payments listed above and other federal funds.) |
|||||||||||
|
9 |
Scioto SR 823 |
19415 |
$158.0 |
$28.75 ARC/Demo |
$25.0 |
Environmental studies for a US 23 bypass of Portsmouth |
$0.5 |
Complete Environmental |
|
|
|
|
9 |
Lawrence SR 7 |
19642 |
$41.2 |
$10.5 Demo/MPO |
$36.0 |
Chesapeake Bypass |
$4.0 |
$14.5 |
|
|
|
|
|
|
19642 |
|
|
|
|
|
$9.0 |
|
|
|
|
|
|
22988 |
|
|
|
|
All Demo |
|
|
|
|
|
9 |
Ross US 35 |
19160 |
$65.0 |
$50.0 ARC |
$15.0 |
New four-lane facility between US 50 and Richmond Dale |
$8.7 |
|
|
|
|
|
10 |
Athens/Meigs US 33 |
18288 |
$87.7 |
|
$87.7 |
Construct Super 2 highway on new location from Athens to Darwin |
|
|
|
|
|
|
|
|
18287 |
|
|
|
|
$44.0 |
|
|
|
|
|
10 |
Meigs SR 124 |
19719 |
$86.1 |
$3.75 Demo |
$82.3 |
Ravenswood Connector |
$21.7 |
|
|
|
|
|
|
|
19738, 19718 |
|
|
|
|
Sold FY 2001 |
|
|||
|
10 |
Washington US 50 Corridor D |
21009/23565 |
$45.0 |
$9.0 ARC |
$36.0 |
Provide access to new Ohio River crossing near Belpre |
APD |
|
$36.0 |
|
|
|
|
|
|
|
|
|
|
$4.5 |
$9.0 |
|
|
|
|
|
|
|
|
|
Total Tier 1 Commitments |
$378.1 |
$363.9 |
$287.8 |
$332.9 |
$126.4 |
|
|
|
|
|
|
|
Southeast Ohio PE and RW Commitments |
$4.5 |
$9.0 |
$0.0 |
$0.0 |
$0.0 |
|
|
|
|
|
|
|
Unanticipated PE and RW |
|
$20.0 |
$30.0 |
$40.0 |
$40.0 |
|
|
|
|
|
|
|
Southeast Ohio Plan Construction Bond Debt Service |
$17.0 |
$17.0 |
$17.0 |
$17.0 |
$17.0 |
|
|
|
|
|
|
|
Projected Change Orders |
$25.0 |
$25.0 |
$25.0 |
$25.0 |
$25.0 |
|
|
|
|
|
|
|
Total Tier 2 Commitments |
$24.4 |
$28.6 |
$16.6 |
$0.0 |
$10.0 |
|
|
|
|||||||||||
|
|
|
|
|
|
|
|
$449.0 |
$463.5 |
$376.4 |
$414.9 |
$218.4 |
|
|
|||||||||||
|
|
|
|
|
|
** Projected Revenue |
$290.0 |
$290.0 |
$290.0 |
$290.0 |
$0.0 |
|
|
|
|
|
|
|
Debt Service Revenue |
$70.0 |
$70.0 |
$70.0 |
$70.0 |
$70.0 |
|
|
|
|||||||||||
|
** - The figures denoted for projected revenue are estimated as a planning tool only. |
Balance |
-$89.0 |
-$103.5 |
-$16.4 |
-$54.9 |
-$148.4 |
|||||
|
|
|||||||||||
|
Cumulative Balance 2002-2006 |
-$412.2 |
||||||||||