409 Sawing And Sealing Asphalt Concrete Pavement Joints

Materials (409.02)

Construction Details (409.03)

Materials (409.02)

Be sure approved materials are used per 409.02 requirements.

Construction Details (409.03)

Check that the following operations are proceeding properly per 409.03:

  1. Intermediate course is saw cut if surface is not placed within 5 days.
  2. Saw cut the surface within 48 hours.
  3. Alignment of saw cuts over joints.
  4. Check saw cut dimensions.
  5. Proper cleaning of the cut.
  6. Length of cut.
  7. Keep clean until sealing.
  8. Proper sealant heating according to manufacturer’s instruction.
  9. Check for backer rod placement, sealant thickness, and uniform placement.