This section recommends minimum documentation and critical
inspection requirements for Items 304,
306, and 307. All of the following documentation
requirements must be recorded in the project daily reports. References to the appropriate
specifications, proposals and plan notes or details for all the inspector
reports are required. Specifications or
other requirements waived by the Project Engineer must be noted on the daily
diaries.
- Roller
weights.
- Lift
thickness.
- Segregation.
- In
place gradation tests according to S-1090,
if required.
- Roller
passes.
- Compaction
tests according to S-1015.
- Verify
cross section and thickness.
- Obtain
weight ticket, if required.
- Verify
design.
- Ensure
of compaction.
- Check
segregation and thickness.
- Check
curing.
- Protection.
- Verify
design.
- Segregation
and thickness.
- Gradation
according to S-1090.
- Roller
weights and passes
- Compaction
according to S-1015.
Protection.