This section recommends minimum documentation and critical
inspection requirements for Items 203, 204, 205, 206, 804, 208, and 209. All of the following documentation
requirements must be recorded in the project daily reports. References to the appropriate laws, specifications,
and proposals and plan notes or details for all the inspector reports are
required. Specifications or other
requirements waived by the Project Engineer shall be noted on the daily
diaries.
Item
203 Roadway Excavation and Embankment
- Verify
plan cross sections.
- Cross
sections of borrow site, if required.
- Classify
suspect soils.
- Foundation.
- Lifts
thickness and roller passes.
- Take
compaction tests according to S-1015.
- Benching.
- Verify
interim quantities.
- Verify
final cross sections.
Item
204 Subgrade Compaction and Proof Rolling
- Compaction
according to S-1015.
- Verify
square yardage.
- Verify
subgrade line and grade.
- Proof
Roll.
- Make
corrections.
- Undercut
measurements.
Item
205 Lime Modified Soil
- Check
contractor design lime percentage.
- Verify
cross sections.
- Lime
spreading rate.
- Lift
thickness and roller passes.
- Compaction
according to S-1015.
- Final
cross sections.
Item
206 Lime Stabilized Subgrade
- Check
Contractor design lime percentage.
- Verify
subgrade line and grade.
- Verify
subgrade stability with test roller, if variable locations.
- Lime
spreading rate.
- Roller
passes.
- Compaction
according to S-1015.
- Fine
Grading.
- Curing.
- Proof
Rolling.
- Make
Corrections.
- Undercut
measurements.
Item
804 Cement Stabilize Subgrade
- Check
Contractor design cement percentage.
- Verify
subgrade line and grade.
- Verify
subgrade stability with proof roller, if variable locations.
- Cement
spreading rate.
- Roller
passes.
- Compaction
according to S-1015.
- Fine
Grading.
- Curing.
- Proof
Rolling.
- Make
Corrections.
- Undercut
measurements.
Item
208 Rock Blasting
- Accept
preblast survey.
- Verify
the experience of the Blasting Specialists.
- Accept
and verify the blasting plan.
- Review
the blasting area for blasting plan dimensions with the blasting
consultant.
- Monitor
the blasting consultants hours.
- Review
the detailed blasting plan of test shots.
- Witness
all shots.
- Check
vibration, airblast and fly rock for all blasts.
- Check
monitoring wells with Hydrologist.
- Presplit
requirement.
- Measure
presplit areas.
- Monitor
blasting consultants hours.
- Review
monthly blasting report.
Item
209 Linear Grading
- Verify
plan dimensions.
- Verify
materials.
- Check
completed work.
- Measure
borrow, if required.