Interstate
275 Hamilton County - District 8
Widening between State Route 42 and Montgomery Rd. Nightly lane closures on I-275
from 9 p.m. to 5:30 a.m.
Start: March 2002/Complete: September 2004
Interstate
275 Clermont County - District 8
Widening between State Route 50 and Beechmont Ave. Nightly lane closures from
9 p.m. to 6 a.m.
Start: June 2002/Complete: June 2004
Interstate
75 Butler/Hamilton County - District 8
Widening project between Interstate 275 and Tylersville Rd. Three lanes will be
maintained in each direction except under the I-275 interchange where two lanes
are being maintained. The ramp from I-275 eastbound to I-75 southbound is reduced
from two lanes to one lane.
Start: March 2003/Complete: June 2005
Interstate
75 Montgomery County - District 7
Construction of a new interchange 1.5 miles south of Interstate 70. Three lanes
of traffic maintained during peak travel times. Lane restrictions may occur between
11 p.m. and 5 a.m.
Start: Spring 2002/Complete: March 2005
Interstate
70 /Interstate 75 Montgomery County - District 7
Reconstruction of various interchange ramps and bridges both on Interstate 70
and Interstate 75. Lane restrictions may occur between 11 p.m. and 5 a.m.
Start: March 2003/Complete: Fall 2006
State
Route 4 Montgomery County - District 7
Resurfacing and bridge replacement from Interstate 75 to south of Harshman Rd.
Two lanes will be open southbound between 6 a.m. and 9 a.m. Two lanes will be
open northbound from 2:30 p.m. to 6 p.m.
Start: Spring 2004/Complete: Fall 2004
State
Route 4 Clark County - District 7
Resurfacing from Interstate 70/State Route 4 interchange to the intersection of
SR 4/Dartmouth St. (just west of SR 4 / U.S. Route 68 interchange) Northbound
SR 4 will close when work begins. Detour route: I-70 east to U.S. Route 68 north
to SR 4.
Start: Spring 2004/Complete: Fall 2004
Interstate
71 Fayette County - District 6
Widening from the Fayette/Greene county line to the village of Jeffersonville.
Work is taking place in the northbound lanes through the end of May. Traffic in
the southbound lanes will not be effected until June 2004. An 11-foot lane-width
restriction is in effect. The
northbound rest area is closed for improvement through spring 2004.
Start: April 2003/Complete: October, 2004
Interstate
70 Madison County - District 6
Major rehabilitation and widening from U.S. Route 42 to State Route 54 in Clark
County. Project will also include rest area improvement. Traffic will be maintained.
Start: July 2004/Complete: October 2006
Interstate
75 Shelby County - District 7
Replacement of two bridges over the Great Miami River. Overnight and off-peak
hour lane closures.
Start: March 2003/Complete: Fall 2004
 |
| |
Project data is applicable during the normal construction season.
(March - November)
|
|
|
|
 |
|
 |