I-70
Madison County
Nighttime lane closures for resurfacing and pavement repair from the Madison/Clark
county line to U.S. Route 42. One lane of traffic will be maintained in each direction
at all times from 8 p.m. to 6 a.m. Short-term ramp closures will also occur at
U.S. 42 and State Route 56. Lane and ramp closures on I-70 are limited to nights
and weekends.
Start: July 2003/Complete: October 2003
I-71 Fayette County
Major reconstruction from the Greene/Fayette county line to Jeffersonville. Two
lanes of traffic will be maintained in each direction. Road closures on various
overpasses will be necessary.
Start: April 2003/Complete: Fall 2004
I-70
Clark County
Widening of four bridges and approximately one mile of pavement to three lanes
in each direction at Enon Rd. An 11-foot width restriction is in effect on I-70.
Overnight and off-peak hour lane closures will occur on I-70. Traffic is maintained
on Enon Rd.
Start: Spring 2002/Complete: August 2003
I-70/I-75
Montgomery County Reconstruction of various interchange ramps and bridges
on both I-70 and I-75. Current lanes of traffic will be available during peak
travel times.
Start: March 2003/Complete: Spring 2006
I-75
Miami County
Widening to three lanes in each direction between Troy and Tipp City. Various
lane closures.
Start: Summer 2000/Complete: September 2003
I-75
Montgomery County
Construction of a new interchange 1.5 miles south of I-70. Three lanes of traffic
maintained during peak travel times. Overnight and off-peak hour lane closures.
Start: Spring 2002 Complete: Fall 2004
I-75
Shelby County
Replacement of two bridges over the Great Miami River.
Overnight and off-peak hour lane closures.
Start: March 2003 Complete: Fall 2004
I-71
Clinton County
Pavement repair from State Route 73 to U.S. Route 68. Lane closure from 9 p.m.
Sunday through noon Friday. All lanes open during the weekend.
Start: July 2003/Complete: November 2003
I-75 Hamilton/Butler County Widening from I-275 to Tylersville Rd. Nightly
lane closures from
9 p.m. to 6 a.m.
Start: March 2003/Complete: Summer 2005
I-75
Warren County
Paving from State Route 122 to the Montgomery County Line. Nightly lane closures
from 9 p.m. to 6 a.m.
Start: April 2003 Complete: September 2003
I-275
Clermont County
Widening from U.S. Route 50 to Beechmont Ave. Nightly lane closures from 9 p.m.
to 6 a.m.
Start: Spring 2002 Complete: November 2003
I-275
Hamilton County
Widening from U.S. Route 42 to Montgomery Rd. Nightly lane closures on I-275 from
9 p.m. to 5:30 a.m.
Start: Spring 2002/Complete: November 2003
I-275
Hamilton/Clermont Counties
Repair pavement and bridges from Montgomery Rd. to U.S. Route 50. Nightly lane
closures from 7 p.m. to 5:30 a.m.
Start: Spring 2002/Complete: July 2003
I-675
Greene County
Paving from State Route 235 to the Clark county Line. Nightly lane closures from
7 p.m. to 6 a.m.
Start: April 2003/Complete: September 2003
|
|
|
Project
data is applicable during the normal construction season. (March - November) |
|
|
 |
|
 |
| Roll over a project
number to view a description |
|
|
|
|
|
|
|