I-70
Muskingum County
Bridge rehabilitation 2.5 miles west of Zanesville. Intermittent lane closures
will occur during night hours.
Start: June 2003/Complete: August 2003
I-70
Muskingum County
Bridge painting at the State Route 797 interchange (airport exit). Intermittent
lane closures will occur during night hours, including weekends.
Start: May 2003/Complete: September 2003
I-70
Guernsey County
Bridge painting one mile west of State Route 723. Intermittent lane closures will
occur during nighttime hours, including weekends.
Start: April 2003/Complete: April 2003
I-70
Guernsey County
Bridge painting near Old Washington. Intermittent lane closures will occur during
nighttime hours, including weekends.
Start: April 2003/Complete: May 2003
I-70
Guernsey County
Bridge painting 4.5 miles east of Old Washington. Intermittent lane closures will
occur during nighttime hours, including weekends.
Start: May 2003/Complete: June 2003
I-77 Guernsey County
Crack sealing between Noble County and Tuscarawas County lines. Intermittent lane
closures will occur during night hours, including weekends.
Start: April 2003/Complete: May 2003
State Route 7 Monroe County
Resurfacing between Hannibal and Clarington. Traffic will be maintained to one
lane during work.
Start: May 2003/Complete: July 2003
State
Route 7 Washington County
Resurfacing between Newport and New Matamoras. Traffic will be maintained to one
lane during work.
Start: June 2003/Complete: August 2003
U.S.
Route 33 Athens County
Major reconstruction through Nelsonville. Travelers may expect changing traffic
patterns throughout project with local detours implemented as needed. Expect delays.
Start: Summer 2002/Complete: October 2003
U.S.
Route 33 Meigs County
Replacement of the Pomeroy-Mason Bridge. Traffic will be maintained on the current
bridge until new bridge is completed.
Start: April 2003/Complete: Summer 2006
I-70
Belmont County
Slip repair in westbound lanes just west of State Route 800. Eastbound lanes will
not be affected. One lane of traffic will be maintained.
Start: July 2003/Complete: August 2003
I-77
Tuscarawas County
Approximately five miles of four-lane major rehabilitation between the Newcomerstown
and Stonecreek exits. One lane of traffic will be maintained in each direction.
Congestion and delays are likely.
Start: March 2003/Complete: Summer 2004
|
|
|
Project
data is applicable during the normal construction season. (March - November) |
|
|
 |
|
| Roll over a project number to view