I-71
Medina County
Widening and reconstruction from one mile south of State Route 18 to the Cuyahoga
county line. Two lanes of traffic will be maintained in each direction.
Start: Summer 2000/Complete: October 2003
I-71
Wayne County
Widening and reconstruction from the Ashland/Wayne county line to the Wayne/Medina
county line. Two lanes of traffic will be maintained in each direction.
Start: Spring 2002/Complete: October 2003
State
Route 8 Summit County
Reconstruction from north of the Central Interchange to the north expressway viaduct
(just north of Perkins St.). Reconstruction of some ramps and elimination of other
ramps. Service roads will be constructed. One lane of traffic in each direction
will occur during non-peak hours. Two lanes of traffic in each direction will
be maintained at all other times. Extensive ramp closures will occur during this
project.
Start: January 2003/Complete: Spring 2005
I-76
Mahoning County
Reconstruction of I-76, reconstruction and widening of Bailey Rd. interchange
ramps to accommodate a left turn lane and rehabilitation of bridges on I-76 at
Newton Falls Rd. and Duck Creek Rd. Two-way traffic will be maintained on I-76.
Start: September 2003/Complete: Fall 2005
I-76
Portage County
Resurfacing and rehabilitation of bridges from just west of County Road 18 for
a distance of eight miles east. One lane of traffic in each direction will occur
during non-peak hours. Two lanes of traffic in each direction will be maintained
at all other times.
Start: Spring 2002/Complete: Summer 2004
I-90
Ashtabula County
Reconstruction and bridge rehabilitation over Conneaut Creek. A minimum of one
lane of traffic will be maintained in each direction using median crossovers.
Start: Spring 2002/Complete: October 2003
I-90
Ashtabula County
Reconstruction and realignment from the Lake County line east to Harpersfield
Township. A minimum of one lane of traffic will be maintained in each direction
using median crossovers.
Start: April 2003/Complete: Fall 2004
I-480
Portage County
Sign replacement from Streetsboro to the Summit County line. Lane closures will
only occur between the hours of 7 p.m. and 6 a.m. when necessary.
Start: May 2003/Complete: August 2003
I-90
Cuyahoga County
Nighttime resurfacing and bridge replacements of I-90 from East 55th St. to just
east of Martin Luther King Jr. Blvd. At least two lanes of traffic will be maintained
in each direction between 8 p.m. to 5 a.m.
Start: July 2003/Complete: Fall 2004
I-90
Cuyahoga and Lake Counties
Reconstruction and add lane on I-90 from State Route 2 to west of State Route
84. At least one lane of traffic will be maintained in each direction between
8 p.m. and 5 a.m.
Start: March 2003/Complete: October 2003
I-90
Lake County
Extending I-90 add lane from west of State Route 306 to east of SR 306. At least
one lane of traffic will be maintained in each direction between 8 p.m. to 5 a.m.
Start: March 2003/Complete: September 2003
I-90
Lake County
Widening of State Route 615 and the addition of an interchange from SR 615 to
I-90.
Start: Summer 2002/Complete: October 2004
I-480
Cuyahoga County
Reconstruction on I-480 from Idlewood Rd. to Tuxedo Ave. Three 10-foot lanes maintained.
Lane addition on I-480 east to State Route 176 north.
Start: March 2003/Complete: Spring 2004
|
|
|
Project
data is applicable during the normal construction season. (March - November) |
|
|
 |
 |
| Roll over a project
number to view a description. Click when rollover description stops. |
|
|
|
|
|
|
|