|
Rating Question No. 1
10 Management personnel are
always available and execute the directions of the engineer.
08 Management personnel are routinely
available and comply with the directions of the engineer.
05 Management personnel are available part of
the time and sometimes offer resistance to the directions of the engineer prior
to compliance.
01 Management personnel are routinely not
available and disagree or disregard the directions of the engineer most of the
time.
Rating
Question No. 2
10 Contractor is always
competent in scheduling work and is very punctual in starting project and
meeting all contract dates.
08 Contractor effectively schedules work
operations carefully and makes a good effort to meet all contract dates.
05 Contractor's work schedule is usually
available and is generally followed to ensure contract dates are attained.
01 Contractor's day to day
operations do not follow work schedule and contract dates are not met.
Rating
Question No. 3
10 The contractor
always has management personnel available who are thoroughly
experienced and knowledgeable in the type of work being performed and have a
thorough understanding of the specifications, plans and special contract
provisions with no instruction needed from the project engineer.
08 The contractor has management personnel
available who are experienced in the type of work being performed and are
familiar with the specifications, plans and contract special provisions with
minimal instruction from the project engineer.
05 The contractor has management personnel
available who are familiar with some of the types of work being performed and
has some knowledge of the specifications, plans and contract special provisions
and requires instruction from the project engineer.
01 The contractor has management personnel
available who have limited knowledge of the type of work being performed and
require constant instructions from the project engineer in interpreting the
specifications, plans and contract special provisions.
Rating
Question No. 4
10 Contractor always staffs the
project with an adequate number of competent workers to perform the work and
continuously monitors their performance.
08 Contractor routinely staffs the project
with enough competent workers to perform the work and monitors their
performance.
05 Contractor staffs the project with
inadequate number of competent workers to perform the work and occasionally
monitors their performance.
01 Contractor does not staff the project with
enough competent workers to perform the work and does not monitor their
performance.
Rating
Question No. 5
10 Contractor always
furnished timely submittals of all required paperwork, documentation, material
reports, time extension notices, claim information, etc. as required with
minimal request.
08 Contractor routinely furnished timely
submittals of all required paperwork, documentation, material reports, time
extension notices, claim information, etc. as required with minimal request.
05 Contractor has to be asked
numerous times to furnish required paperwork, documentation, material reports,
time extension notices, claim information, etc.
01 Contractor does not furnish required
paperwork, documentation, material reports, time extension notices, claim
information, etc. in a timely manner and must be asked in writing.
Rating
Question No. 6
10 The contractor always
informed the project engineer of his daily schedule of
operations.
08 The contractor routinely informed the
project engineer of his daily work schedule.
05 The contractor informed the project
engineer of his daily work schedule after repeated
notifications.
01 The contractor informed the
project engineer of his daily work schedule only after written
notification.
Rating
Question No. 7
10 The contractor
always followed chain of authority by initiating all requests and
communications through the project engineer.
08 The contractor routinely followed chain of
authority by initiating requests and communications through the project
engineer.
05 The contractor occasionally followed the
chain of authority by initiating requests and communications through the project
engineer.
01 The contractor did not follow the chain of
authority by initiating requests and communications through the PE/PS.
Rating
Question No. 8
10 The contractor always
complied with the direction from the project engineer.
08 The contractor routinely complied with the
direction from the project engineer.
05 The contractor complied with the direction
after repeated notification from the project engineer.
01 The contractor complied only upon written
direction from the project engineer.
Rating
Question No. 9
10 The contractor
always conducted his work so as not to interfere with or hinder the
work of other contractors on adjacent projects.
08 The contractor routinely
conducted his work so as not to interfere with or hinder the work of other
contractors on adjacent projects only
after notification from the project engineer.
05 The contractor conducted
his work so as not to interfere with or hinder the work of other contractors
only after repeated notification from the
project engineer.
01 The contractor conducted
his work so as not to interfere or hinder the work of other contractors only
upon written notice from the project engineer.
Rating Question No. 10
10 This contractor has no
documented violations of the ODOT contract specifications relating to Labor
Standards/Wage-Rate Compliance and prompt payment.
08 The contractor had
documented violations of the ODOT contract specifications relating to Labor
Standards/Wage-Rate Compliance and prompt payment.
However, these violations were immediately corrected upon notification by the
Department.
05 The contractor had
documented violations of the ODOT contract specifications relating to Labor
Standards/Wage-Rate Compliance and prompt payment.
These violations were corrected only after repeated notification by the
Department.
01 This contractor has
numerous documented violations of the ODOT contract specifications relating to
Labor Standards/Wage-Rate Compliance and prompt payment
which were not corrected.
Rating Question No. 11
10 Contractor always complied
with all EEO laws and regulations, and provisions for on the job
training. appropriate D.B.E. regulations.
08 Contractor complied with all EEO laws and
regulations, and provisions for on the job training
appropriate D.B.E. regulations after
notification from by the
project engineer Department.
05 Contractor complied with all EEO laws and
regulations, and provisions for on the job training
appropriate D.B.E. regulations after repeated
notification from by the
PE/PS Department.
01 Contractor did not comply with all EEO laws
and regulations. and provisions for on the job training.
appropriate D.B.E. regulations.
Rating Question No. 12
10 Contractor always provided
the appropriate numbers and types of equipment to do the work.
08 Contractor did not always
provide the appropriate numbers and types of equipment to do the work. However,
this did not substantially effect the progress of the project.
05 Contractor did not always
provide the appropriate numbers and types of equipment to do the work which
effected the progress of the project.
01 Contractor did not provide
the appropriate numbers and types of equipment to do the work.
Rating Question No. 13
10 Equipment breakdowns that
may have occurred did not impede the progress of the project.
08 Equipment breakdowns that
occurred caused minimal delay to the project.
05 Equipment breakdowns that
occurred impeded the progress of the project.
01 Equipment breakdowns
severely impeded the progress of the project.
Rating Question No. 14
10 Contractor always maintained
the work site in a safe and clean condition.
08 Contractor often maintained
the work site in a safe and clean condition and immediately corrected
deficiencies upon notification from the project engineer.
05 Contractor maintained the
work site in a safe and clean condition after repeated notification from the
project engineer.
01 Contractor did not maintain
the work site in a safe and clean condition.
Rating Question No. 15
10 Contractor always
assigned an individual to continually monitor and maintain all traffic control
requirements. Any job site conditions which effected the traveling public were
corrected immediately (even after hours) with no direction from the project
engineer.
08 Contractor assigned an
individual to continually monitor and maintain all traffic control requirements.
Most deficiencies were immediately corrected without notification by the project
engineer.
05 It was necessary to notify
the contractor of traffic control deficiencies. The deficiencies were corrected
upon notification from the project engineer.
01 Contractor required
continual notification of job site deficiencies in traffic control requirements.
Deficiencies were corrected only after written notification by the project
engineer.
Rating Question No. 16
10 Contractor always complied
with the contract requirements.
08 Contractor routinely
complied with the contract requirements. Any non-compliances were immediately
corrected upon notification from the project engineer.
05 Non-compliances were
corrected only upon repeated notification from the project engineer.
01 Contractor complied with
contract requirements only upon written order of suspension of work from the
project engineer.
Rating Question No. 17
10 The contractor did not have
to remedy or remove any defective work.
08 It was necessary for the
contractor to make minor repairs and corrections to the work.
05 It was necessary for the
contractor to make numerous repairs to the work.
01 It was necessary for the
contractor to remove or correct a substantial amount of work due to poor
workmanship.
Rating Question No. 18
10 The contractor
always provided advance notifications to all potentially effected
utilities prior to commencing work and did whatever was necessary to cooperate
with the utility and protect their existing facility.
08 The contractor routinely
provided proper notification and cooperated with each effected utility company.
Documented problems existed but were immediately corrected by the contractor.
05 The contractor provided
proper notification to all effected utilities after direction from the project
engineer. Documented problems existed where the contractor did not cooperate
fully with the utility company in protecting the existing facility.
01 The contractor did not
provide the proper notification to the effected utilities and/or after
notification, did not make an effort to cooperate with the utility company nor
protect the existing facility.
Rating Question No. 19
10 Contractor always
scheduled and conducted operations to avoid urgencies.
08 Contractor attempted to
schedule and conduct operations to avoid urgencies. Any problems created were
immediately corrected.
05 Contractor's scheduling and
conducting of operations created urgencies which were corrected only upon
direction of the project engineer.
01 Contractor did not schedule
and conduct operations to avoid urgencies.
Rating
Question No. 20
10 The contractor performed
final clean-up on or before the completion date and received no punch list.
08 The contractor performed
final clean-up on his own and once given the final punch list, completed the
work on or before the specified date.
05 The contractor completed
the final clean-up and the punch list only after repeated notification from the
project engineer.
01 The contractor did not
complete the final clean-up and the final punch list in a timely manner.
Rating Question No. 21
10 The contractor
always coordinated work operations with its subcontractors.
08
The contractor routinely coordinated all work operations with its
subcontractors.(sub-subcontractors).
When coordination did not occur, this did not substantially
effect the progress of the project.
05 The contractor coordinated
work operations with its subcontractors (sub-subcontractors) only upon
notification from the project engineer.
01 The contractor did not
coordinate work operations with its subcontractors.
Rating Question No. 22
10 Contractor always
exercised authority over subcontractors and provided notice of subcontractor
schedule at all times.
08 Contractor routinely
exercised authority over subcontractors and provided notice of subcontractor
schedule most of the time.
05 Contractor exercised
authority over subcontractors and provided notice of subcontractor schedule only
upon notification from the project engineer.
01 Contractor did not exercise
any authority over subcontractors and/or did not provide notice of
subcontractors' work schedule.
Rating Question No. 23
10 Contractor always
monitored subcontractors' activities to ensure approved materials were supplied
and incorporated into the project at all times.
08
Contractor routinely monitored subcontractors' activities to ensure approved
materials were supplied and incorporated into the project.
Any problems were corrected
immediately upon notification by the project engineer.
05 Contractor monitored
subcontractors' activities to ensure approved materials were supplied and
incorporated into the project only
upon repeated notification from the
project engineer.
01 Contractor did not monitor
subcontractors' activities to ensure approved materials were supplied and
incorporated into the project at all times.
Rating Question No. 24
10 Contractor always
ensured subcontractors submitted all paperwork required for approvals,
materials, and payrolls in a timely manner.
08 Contractor routinely
ensured subcontractors submitted all paperwork required for approvals,
materials, and payrolls in a timely manner with minimal notification from the
project.
05 Contractor ensured
subcontractors submitted all paperwork required for approvals, materials, and
payrolls in a timely manner with repeated notification from the project.
01 Contractor did not ensure
subcontractors submitted all paperwork required for approvals, materials, and
payrolls in a timely manner. Information had to be requested in writing.
(Revised C-95)
A.
ORGANIZATION AND MANAGEMENT
1) To what degree are
management personnel available with full authority to execute the directions of
the engineer ?
2) To what degree are
management personnel competent and effective in scheduling the work and
organizing construction operations, including being punctual in starting and
completing the work on the project and meeting critical intermediate phases in
accordance with the approved progress schedule ?
3) To what degree did
management personnel have the knowledge necessary regarding specifications,
plans and the special provisions?
4) How adequately was the
project staffed with competent workers who were monitored ?
5) To what degree did the
contractor furnish the required documentation and reports in a timely manner (ie.
Certification of materials, delivery tickets, invoices, progress schedule, shop
drawings, material sampling, early notice of time extension, potential claims,
etc.) ?
6) Did the contractor inform
project personnel in advance of scheduled day to day items of work ?
7) To what degree was the
chain of authority in the department respected by the contractor (positive
attitude toward project personnel, etc.) ?
8) Did the contractor comply
with the direction of project personnel without delay ?
9) To what degree did the
contractor cooperate with other contractors performing work on adjacent projects
?
10) Did the contractor comply
with all wage rates and labor regulations, and submit accurate certified
payrolls and promptly pay all subcontractors and
material suppliers?
11) Did the contractor comply
with all EEO laws and regulations, and on-the-job training special
provisions appropriate D.B.E. regulations?
B. EQUIPMENT
12) Did the contractor provide
the appropriate number and type of equipment necessary for performance of the
work ?
13) Did the contractor provide
preventative maintenance and repairs of equipment to ensure against breakdowns
which would impede the progress of the project ?
C. WORK PERFORMANCE
14) To what degree was the work
site maintained in a safe and clean condition ?
15) To what degree did the
contractor maintain adequate signs, lights, barricades, and properly trained
flagpersons in accordance with Ohio Manual of Uniform Traffic Control Devices,
traffic control plan and approved revisions ?
16) To what degree did the
contractor meet contract requirements including specifications, supplemental
specifications, special provisions, plans, and supplementary
documents and erosion control with
minimal instruction from the department ?
17) To what degree did the
contractor provide attention to the quality of work performed eliminating the
need to remedy or remove defective work ?
18) To what degree did the
contractor properly notify and coordinate work with utility companies in
protection of existing utilities ?
19) To what degree did the
contractor minimize urgencies of construction that required ODOT to compromise
the quality of work or abandon good construction practices in order to complete
the project. (ODOT forced to allow poor weather paving, incorporate
non-specified material, etc.) ?
20) To what degree were final
clean up and punch list items complete ?
D. SUBCONTRACTOR MANAGEMENT
(SUB-SUBCONTRACTOR)
21) To what degree did the
contractor coordinate work with subcontractors work ?
22) To what degree did the
contractor exercise authority over subcontractors and provide notice of
subcontractor work schedule ?
23) To what degree did the
contractor monitor subcontractor activities to ensure approved materials were
supplied and incorporated into the project ?
24) To what degree did the
contractor ensure that subcontractors submitted all paperwork required for
approvals, materials, and payrolls ?
|